Project Timeline

ORIGINAL GOAL: begin connecting subscribers by year-end 2009

NEW GOAL: Begin connecting subscribers one year after closing on funding.

  • Fall 2007 - Winter 2008: Selectboard Community info meetings; pre- subscriptions begin December 2007; Towns vote on Town Meeting Day
  • April 2008: Inter-local agreement made among towns
  • July 2008: Work begins to obtain financing.
  • October-December 2008: Towns sign final documents, financial offering made, closing on financing.

    This is when the economic meltdown occurred.

  • The following milestones are planned:
  • Network design: 6 months
  • Construction begins: 6 months
  • Connection of the first customers begins Connections proceed continuously as new areas are wired. Pre- subscribers are connected first in any area that is wired
  • Complete wiring of entire ECF territory: approximately 2 years